Conduit installation

Stub-Up Bend Calculator

Find the 90-degree conduit stub-up mark from the desired finished height and the take-up specified for your bender.

Conduit geometry

Bend details

in
in

Default is a common 1/2 in EMT hand-bender value. Use the take-up marked on your bender or in its manual.

Mark locations

90° stub-up mark from conduit end
5 in
Desired stub height10 in
Bender take-up5 in

Mark = desired stub height − bender take-up.

Geometry aid onlyDisplayed marks are rounded to the nearest 1/16 in. Confirm take-up, multipliers, bend radius, and mark-pointer alignment for your conduit and bender. Make a test bend and verify the finished dimensions.

Method and field check

The mark location equals desired finished stub height minus bender take-up. Take-up varies by bender, conduit size, and material. Use the value marked on the bender or in its instructions and verify the result with a test bend.